The Daily Plan allows you to view the work calendar and the scheduled activities for each resource for the selected day.
Using the Options button available in the Gantt view, you can configure which warning types should be enabled, allowing you to customize the information displayed according to your operational needs.
Access the Daily Plan Warnings
To access the Daily Plan tab:
-
Navigate to Features > Core > Daily and Multi-day Plan > Daily Plan.
-
Click the three-dots button located in the top-left of the gantt view of the Daily Plan
-
Click the “Warning” tab
|
Warning Type |
Warning field |
Functional Description |
|
Scheduling |
Shift to validate |
The shift contains planned activities not yet validated/sent to mobile |
|
Overtime |
There are planned activities beyond the working hours defined in the calendar |
|
|
Exceeding competence slot |
Activities scheduled outside the expected competence time window for the operation |
|
|
Non-consistent skills |
The resource's skills do not fully cover those required by the assigned activities |
|
|
Violation of Materials |
The resource's mobile warehouse is insufficient relative to the materials required by the activities (RELATED TO OLD INTEGRATION WITH NETA SOLUTIONS) |
|
|
Tools not available |
The tools required by the activity are not available |
|
|
Planned outside manned facility |
A resource allocated to monitor a plant has been assigned tasks outside this plant |
|
|
Scheduling removal proposal |
A scheduling removal exists for the activity. |
|
|
Accounting |
Work exceeding shift |
Debriefing/outcomes recorded beyond the planned work shift |
|
Undebriefed time intervals |
Workable intervals within the shift that have not yet been debriefed |
|
|
Overlapping outcomes |
Recorded outcomes with overlapping time ranges |
|
|
Outcomes to be validated |
Outcomes/debriefings present but not yet validated |
|
|
Clocking |
Missing clocking |
The technician has not performed the expected clock-in/out |
|
Clocking not closed |
The technician clocked in but did not clock out at the end of the shift |
|
|
Clocking not consistent with work shift |
Anomalous deviation between clocking times and the scheduled work shift |
|
|
Multistage |
Multistage group scheduling violation |
The multistage group is only partially scheduled (at least one operation still schedulable or to be rescheduled) |
|
Critical multistage dependency violation |
Critical dependency not satisfied: SS/SF with only one scheduled; FS with successor scheduled but predecessor not. Warning applied to both activities. |
|
|
Time multistage dependency violation |
The time constraint (min/max window) defined on the dependency is not satisfied. Warning applied to both activities. |
|
|
Critical Activity |
Activity not yet validated |
Critical/Jeopardy activity scheduled but not yet validated within the threshold defined by the rule |
|
Activity not yet in charge |
Critical/Jeopardy activity not yet taken in charge within the threshold defined by the rule |
|
|
Activity taken in charge and not yet started |
Critical/Jeopardy activity already taken in charge but not yet started within the threshold defined by the rule |
|
|
Activity not yet started and arrival on site set |
Resource has arrived on site but the critical activity has not yet been started within the threshold defined by the rule |
|
|
Crew Shell |
Empty crew shell |
The crew shell has no members assigned for the day |
|
Minimum cardinality |
The number of active members is below the minimum cardinality required by the crew definition |
|
|
Crew members skills |
The members' competencies do not cover the full set of skills required by the crew shell |
|
|
Lunch breaks |
The lunch break time of at least one member is not aligned with that of the crew shell |
|
|
Calendar hours |
The working hours of at least one member do not cover the full time window of the crew shell |