Debrief measurement interventions on the daily plan

Audience: Dispatchers

Record intervention details and a measurement for each measuring element related to a work order (WO). Specific objects can be related to a work order (WO) and be associated with measuring elements that record data at specific times. To help organize data, these measurements can also be reflected on the daily plan.

Prerequisites

Before you start:

Follow the UI path

All following instructions start from this system path:

  1. Navigate to Features > Core > Daily and Multi-day plan > Daily Plan.

  2. In the Filters panels, enter:

    • Operations center.

    • Date.

    • Any other applicable information.

Debrief a measure from the daily plan

To view the activity outcome for a specific planned order:

  1. On the Daily plan page, right-click a scheduled activity.

  2. Select Accounts > Activity outcome.

  3. On the Measurements tab view the summary table.

Note: For each intervention, you can only register one measurement per measuring element.

Add a measure

To register a measure:

  1. To add a value, click on the individual row of interest. 

  2. Click the measuring element for the data.

    • For example, Pressure.

  3. To register the value, fill in the Value field.

  4. Click Save.

Understand progress icons

To facilitate operations, the table uses visual indicators that immediately show the progress of the measurements:

  • Green (Measure executed): Highlights measures that already have a value.

  • Red (Measure to execute): Highlights measures that don’t have a value.

What’s next