Manage daily variations in a resource’s schedule. Allow for day-specific adjustments to a resource’s shifts, locations, and service territory.
Add calendar objects
To add information about resource availability:
-
Navigate to Features > Core > Resource Management > Resources.
-
In the search window, select an operations center from the drop-down.
-
Click Search.
-
In the Scheduling resources table, click the Three dots menu to the left of the resource.
-
Click Define Calendar.
-
In the Defining user calendar table, click the Plus icon on a weekday.
-
In the new window, select one:
-
New Shift: Add a new work shift for the resource.
-
New On Duty Availability: Specify when the resource is available.
-
New Absence: Add a vacation period for a resource.
-
New Extra Presence: Add a resource to cover an absent resource’s work shift.
-
-
Enter the required information.
-
Click either:
-
Save.
-
Confirm.
-
Edit a calendar
To edit a calendar for a resource in the Defining user calendar table:
-
In the workday row, click the three dots menu.
-
Click one:
-
Modify: For the day, change a resource’s work shift.
-
Associate Base Point: For the day, change where the resource is based.
-
Associate scheduling area: For the day, change the resource’s scheduling area.
-
Remove: Remove the resource’s shift.
-
-
Enter the required information.
-