NextGen FSM

Add simulated timeframes

The Activity Forecast feature allows you to simulate demand by configuring various types of tasks.

You can create forecasts based on either:

  • Real activities and operations already present in the system.

  • Simulated activities

A significant advantage of using activity forecasts is their complete independence from actual activities and work-orders data. This means any adjustments or edits made within the forecast simulation will not impact the live operational data in your system.

Before you start

Add simulated timeframes

  1. In the FSM App, navigate to FEATURES → FORECASTING & CAPACITY PLANNING → ACTIVITY FORECAST

  2. Use the filter panel to search for existing forecast records

  3. Clicking the option button related to the Activity Forecast, going on “Detail” option the configuration page will be showed as a gantt view.

  4. Right-click on an activity row

  5. OPTION 1: Click “Add Timeframe” to add a single timeframe using the form.

  6. OPTION 2: Click “Add Multiple timeframes” to add more timeframes using the form.

Form - Add one timeframe

Field

Description

Start Date

start date of the execution period

End Date

end date of the execution period

Priority

priority level

Grouping Constraint

grouping constraint to associate to the activity, only one for each timeframe

Mode

mode to define the activity duration. It can be “Expected Duration” and “Number of tasks”. They are exclusive.

Expected Duration (minutes)

the total duration of the timeframe expressed in minutes.


Number of Tasks

number of tasks to execute in the defined period

Average Task Duration (minutes)

average time of each task in the defined period

The “Refresh” icon

It allows to compute expected duration also when the selected Mode is “Number of Tasks”. It is not possibile the otherwise.

  • Expected Duration (minutes) = Number of Tasks * Average Task Duration (minutes)

Form - Add multiple timeframes

Field

Description

Start Date

start date of the execution period

End Date

end date of the execution period

Every

to define how often the timeframe starts

Timeframe Duration (days)

duration of each single timeframe expressed in days

Priority

priority level

Grouping Constraint

grouping constraint to associate to the activity, only one for each timeframe

Mode

mode to define the activity duration. It can be “Expected Duration” and “Number of tasks”. They are exclusive.

Expected Duration (minutes)

the total duration of the timeframe expressed in minutes.


Number of Tasks

number of tasks to execute in the defined period

Average Task Duration (minutes)

average time of each task in the defined period

The “Refresh” icon

It allows to compute expected duration also when the selected Mode is “Number of Tasks”. It is not possibile the otherwise.

  • Expected Duration (minutes) = Number of Tasks * Average Task Duration (minutes)

The “Generate Preview” button allows to evaluate the result through a timeframe table, before to save it.

Edit a timeframe

To edit a timeframe already created, right-click on the timeframe and it will be possibile to edit or delete a timeframe.

The edit option will open the same creation panel, and it will be possibile to edit all parameters.

A tooltip on each timeframe will show some information about it:

  • Start Date

  • End Date

  • Expected Duration (minutes)