NextGen FSM
2026 Wave Two 2026 Wave Three 2026 Wave One
2026 Wave Two 2026 Wave Three 2026 Wave One

Reference: Daily plan emergency response archive

Follow the UI path

Open the emergency response archive:

  1. Navigate to Features > Core > Daily and Multi-day Plan > Daily Plan.

  2. In the Filters panel, enter desired parameters.

  3. Click Search.

  4. On the Daily plan page, click the Emergency response tab.

  5. Click the Archive button.

Processing list

In the archive, the Processing list provides a high-level view of each emergency response execution. The list allows the user to identify runs with many exclusions, failed assignments, or reprocessing activity.

Column

Description

Id

The ID of the emergency response

Operation center

The operation center (OC) for which the processing run was executed

Scheduling model

The emergency response model used for the processing run

State

The status of the run

Reprocessing

Whether the run included the reprocessing phase

Expected processing date

When the emergency response should be processed

Processing start date

The date related to the start of the processing run

Processing end date

The date related to the end of the processing run

WO assigned

The number of the urgent WOs assigned

WO not assigned

The number of the urgent WOs not assigned

Excluded resources tab

The Excluded resource tab lists each resource or technician's excluded from the selected processing run and the reason for exclusion:

Column

Description

Resource id

The ID of the resource, technician or foreman excluded from the processing run

Team id

The ID of the team associated with the excluded resource

Resource

The name of the resource, technician or foreman excluded from the processing run

Exclusion reason

The reason why the resource was excluded

Typical exclusion causes include:

Causal

Meaning

TOO_FAR

The resource is beyond the configured maximum straight-line distance.

NO_FEEDBACK

The latest mobile/GPS feedback is older than the configured threshold.

NO_SHIFT

The resource doesn’t have a valid shift for the selected day.

SHIFT_END

The remaining shift time is below the configured minimum threshold.

SHIFT_START

The shift hasn’t started yet and the start time is outside the configured inclusion window.

NO_SKILL

The resource does not have the skills required by the urgent WO operation.

CLOCKING

The resource hasn’t clocked in although it’s required by the configured clocking rule.

CREW_SHELL

The resource belongs to an unsupported crew shell configuration.

MIXED_TEAM

The resource works in a team configuration not supported by emergency response.

MULTI_DAY

The resource is in an unsupported multi-day activity scenario.

MANDATORY_RESOURCE

The resource isn’t included in the mandatory resources defined on the WO.

EXCLUDED_RESOURCE

The resource is explicitly excluded from the WO.

Emergency response activities tab

The Emergency response activities tab shows the urgent work order (WO) considered during the selected processing run:

Column

Description

WO operation id

The internal WO code.

WO operation

The specific operation code of the WO.

Foreman

The foreman of the team

State

The status of the assignment

Creation date

When the emergency response process was created

Last processing date

The last processing date of the emergency response task

Processing counter

The number of times when the WO was processed by the emergency task

Last processing error

When the last processing error occurred 

Planning changes tab

The Planning changes tab provides a detailed record of every change made to the operational plan during the reprocessing phase. Once the emergency response assignment is fixed, the remaining non-urgent activities are assigned to the resources.

Field

Description

Resource

Who performed the emergency response

Activity code

The code of the activity associated with the emergency response

Confirmed

If the intervention was confirmed

Cancelled

If the intervention was cancelled

New

If the intervention was new

Original resource

The technician who requested an emergency response

Recipient resource

The technician who received the emergency response request

What’s next